# Effects of Variable Load on Power Station

- Link: https://studyelectrical.com/2015/06/effects-of-variable-load-power-station.html
- Published: 2015-06-10T05:36:00+00:00
- Author: 

The load on a power station varies from time to time due to uncertain demands of
the consumers and is known as the **variable load on the station**. 

 

[⌊Variable%2Bload%2Bon%2Bpower%2Bstation⌉⌊Variable%2Bload%2Bon%2Bpower%2Bstation⌉[

A power station is designed to meet the load requirements of the consumers. An ideal
load on the station, from standpoint of equipment needed and operating routine, 
would be one of constant magnitude and steady duration.

However, such a steady load on the station is never realized in actual practice.
The consumers require their small or large block of power in accordance with the
demands of their activities. 

 

Thus the load demand of one consumer at any time may be different from that of the
other consumer. The result is that load on the power station varies from time to
time. 

### Effects of variable load on Power Station

The variable load may cause many problems in the operation of a power station. Some
of the important effects of variable load on a power station are : 

#### **_The need for additional equipment_**

The variable load on a power station necessitates having additional equipment. By
way of illustration, consider a steam power station. Air, coal, and water are the
raw materials for this plant. 

 * In order to produce variable power, the supply of these materials will be required
   to be varied correspondingly. 
 * For instance, if the power demand on the plant increases, it must be followed
   by the increased flow of coal, air, and water to the boiler in order to meet 
   the increased demand. 
 * Therefore, additional equipment has to be installed to accomplish this job. 

As a matter of fact, in a modern power plant, there is much equipment devoted entirely
to adjust the rates of supply of raw materials in accordance with the power demand
made on the plant. 

#### **_Increase in production cost_**

The variable load on the plant increases the cost of the production of electrical
energy. An alternator operates at maximum efficiency near its rated capacity. 

 * If a single alternator is used, it will have poor efficiency during periods of
   light loads on the plant. 
 * Therefore, in actual practice, a number of alternators of different capacities
   are installed so that most of the alternators can be operated at nearly full 
   load capacity. 

However, the use of a number of generating units increases the initial cost per 
kW of the plant capacity as well as the floor area required. This leads to an increase
in the production cost of energy. 

### Effect of Variable Load on Power Plant Design

The characteristics and method of use of power plant equipment is largely influenced
by the

extent of variable load on the plant.

Supposing the load on the plant increases. This will reduce the rotational speed
of the turbo-generator. The governor will come into action operating a steam valve
and admitting more steam and increasing the turbine speed to its normal value. This
increased amount of steam will have to be supplied by the steam generation. The 
governor response from load to the turbine is quite prompt, but after this point,
the governing response will be quite slower.

 * Variable load results in fluctuating steam demand. Due to this, it becomes, very
   difficult to secure good combustion since efficient combustion requires the coordination
   of so many various services.
 * The variable load requirements also modify the operating characteristics built
   into equipment. Due to non-steady load on the plant, the equipment cannot operate
   at the designed load points. Hence for the equipment, a flat-topped load efficiency
   curve is more desirable than a peaked one.

### Effect of Variable Load on Power Plant Operation

In addition to the effect of variable load on power plant design, the variable load
conditions impose operation problems also, when the power plant is commissioned.

Even though the availability for service of the modern central power plants is very
high, usually more than 95%, the public utility plants commonly remain on the “readiness-
to-service” bases. Due to this, they must keep certain of their reserve capacity
in “readiness-to-service”. This capacity is called “spinning reserve” and represents
the equipment standby at normal operating conditions of pressure, speed etc.

In a steam power plant, the variable load on electric generation ultimately gets
reflected on the variable steam demand on the steam generator and on various other
equipment. The operation characteristics of such equipment are not linear with load,
so, their operation becomes quite complicated.

As the load on electrical supply systems grow, a number of power plants are interconnected
to meet the load. The load is divided among various power plants to achieve the 
utmost economy in the whole system.

When the system consists of one baseload plant and one or more peak load plants,
the load in excess of baseload plant capacity is dispatched to the best peak system,
all of which are nearly equally efficient, the best load distribution needs thorough
study and full knowledge of the system.

 