# Condition Monitoring for Transformers

- Link: https://studyelectrical.com/2014/06/condition-monitoring-of-transformers.html
- Published: 2014-06-09T16:47:00+00:00
- Author: 

Condition monitoring for transformers is the process of monitoring a parameter of
conditions in transformer (moisture, temperature, etc.), in order to identify a 
significant change which is indicative of a developing fault.

Power transformers are critical and costly assets in the electric power system beginning
with the grid, transmission, and down to the plant. They are one of the most important
electric apparatus for providing reliable energy flow. 

As an asset class, transformers constitute one of the largest investments in a utility’s
system or in an industrial complex. For this reason, transformer condition assessment
and management is a high priority.

Each entity is unique and the investment levels in asset condition and assessment
management vary according to the risk level and investment return models.  

The transformers are stratified according to the criticality of individual transformers
and in this approach, the most critical transformers receive the highest investment
of condition assessment and management tools and less critical and non-critical 
transformers receives the decreased level of asset allocations.[⌊pt⌉](http://3.bp.blogspot.com/-3ylg8T91LsI/U5Xd4sny2DI/AAAAAAAAA8w/cwevy3ziSCk/s1600/pt.jpg)

The performance expectation of a transformer is:

 * **Transfer of voltage level**
 * **Supply of required loads and**
 * **Accommodating voltages fluctuations to a specified range **

**Need for Condition Monitoring**

 * Expensive capital equipment
 * Not easy to repair or replace
 * Advanced computer-aided design practices.
 * Transformers operation.
 * Condition Monitoring imperative.
 * A corrective/preventive action can be initiated

### Types of Condition Monitoring

The condition monitoring of transformer may be classified as:

 1. **Working condition monitoring**
 2. **Emergency condition monitoring**

The first is to watch all the parameters and take corrective actions to keep them
within specified limits, whereas the second is to bring out the equipment from the
working system by sharp monitoring of the type of emergency occurs.

### Working Condition Monitoring of Transformer

The working conditions of transformers in the [substation](https://studyelectrical.com/2019/04/electrical-substation-equipment-types-components-functions.html)
are classified as “ATTENDED” but those in distribution are classified as “UNATTENDED”.
Hence, condition monitoring differs and classified as follows: 

 * Continuous monitoring (hourly monitoring) for transformers in the [substation](https://studyelectrical.com/2019/04/electrical-substation-equipment-types-components-functions.html)
 * Random monitoring in case of [distribution transformers](https://studyelectrical.com/2014/11/power-transformers-and-distribution-transformers.html)

The objective of transformer maintenance is to safeguard against breakdowns by detecting
potential causes and eliminating them. Therefore, periodic transformer maintenance
will ensure many years of trouble-free operation. 

Transformer maintenance schedules should determine according to the critical or 
noncritical nature of the transformer and the load that is connected to it.

A transformer that has been operating satisfactorily for many years may, because
of neglection, suddenly fail without warning or any outward sign of distress thereby
causing expensive repairs or replacement and loss of production.

The term maintenance as applied to transformers consists of:

 1. keeping all peripheral parts clean and protected from dust, dirt, and corrosion
 2. testing the winding insulation,core, insulating and cooling liquid to check its
    suitability to onward use
 3. inspecting and testing the protective and indicating devices for its healthiness
 4. inspecting the transformer internally for any abnormalities
 5. inspecting the auxiliary equipment such as fan, coolers, [lightning arrestors](https://studyelectrical.com/2014/06/lightning-arrester-location-rating-and.html)
    and grounds, etc. for soundness

Although a transformer with its associated equipment does not have as many moving
parts as most of electrical pieces of equipment, the same rules still apply.

These basic rules are:

 1. current-carrying components must operate in a moisture-free insulating liquid or
    area
 2. the installation must be kept clean from dirt, rust or corrosion
 3. all moving parts must be kept well-lubricated
 4. all enclosures containing insulating and cooling liquids as well as weatherproof
    enclosures that protect the equipment from the weather must be kept tight 

### Frequency of Inspection and Maintenance

Frequency on Inspection of a transformer depends upon:

 * Size
 * Type
 * Existing practice
 * Prevailing atmospheric conditions

Frequency of inspection and maintenance greatly depend upon size and type of the
transformer and also on the prevailing atmospheric condition at site and by existing
practice and experiences.

Normally the large power transformers supplying critical load should receive more
frequent inspection and maintenance rather than small transformers delivering lighting
loads or less critical circuits. 

For a particular transformer, a maintenance schedule can be fixed in consultation
with supplier. Once a schedule has been established it should be closely followed
and various events shall be recorded.

A general guideline of transformer maintenance is laid down and shall be modified
to suit the actual equipment under use. Before starting any maintenance work safety
regulations enforced must be strictly observed.

### Typical Condition Monitoring Schedule of Transformer

The typical condition monitoring schedule of a transformer is given below.

  |

**SI.**

**No.**

  |

**Inspection Frequency**

  |

**Items to be Inspected**

  |

**Inspection Notes**

  |

**Action Required if Inspection shows Unsatisfactory Conditions**

  |  
 |

1

  |

Hourly

  |

1) Ambient Temp.

2) Winding Temp.

3) Oil temperature.

4) Load(amperes)

5) Voltage

6) Free delivery of water in case of water-cooled transformer

7) Check for full flow indication by oil flow indicator

  |

Check that temperature rise is reasonable

Check against rated figures

Check for oil traces in the water at outlet

Ensure that a sufficient quantity of oil flow

  |

Shut down the transformer and investigate if either is persistently higher than normal

Isolate heat exchanger and put the stand by in the circuit. Rectify leak in the faulty heat exchanger

  |  
 |

2

  |

Daily

  |

1) Oil level in transformer

2) Oil level in bushings

3) Leakage of water into the cooler

4) Relief vent diaphragm

5) Dehydrating breather

6) Oil level in OLTC conservator

7) Pressure relief diaphragm of OLTC DS chamber

  |

Check against transformer oil temperature

     

                 –

Check that air passages are free.

Check the colour of the active agent

Low/Increasing/Overflowing

Check for damage

  |

If low, top up with dry oil, examine transformer for leaks

If low bring it to correct oil level

Replace if cracked or broken

Replace if cracked or broken

If silica gel is pink, change by spare charge. The old charges may be reactivated for reuse.

Replenish oil if low. If increasing  or overflowing check for oil leakage from the main tank to OLTC DS chamber

Replace by new one

  |  
 |

3

  |

Quarterly

  |

1 ) Bushing

2) Oil in the transformer

3) Cooler fan bearings, motors, and operating mechanism

4) OLTC

5) Indoor transformers

  |

Examine for cracks and dirt deposits

Check for dielectric strength and water content

Lubricate bearings. Check gearbox.

Examine contacts.

Check manual control and interlocks

Check oil in OLTC driving mechanisms

Check ventilation

  |

Clean or replace

Take suitable action to restore the quality of oil

Replace burnt or worn contacts or other parts

Filter or replace

  |  
 |

4

  |

Half Yearly

  |

Oil cooler

  |

Test for pressure

  |

  |

  |

5

  |

Yearly (or earlier if, the transformer can be conveniently be taken out for checking)

  |

1)Oil in the transformer

2)Oil filled bushings

3)Gasket joints

4)Cable boxes

5)Surge diverter and gaps

6) Relays, alarms, their circuits, etc.

7)Earth resistance

8)Winding

  |

Check for acidity and sludge. DGA

Check for tan delta and Capacitance

Check for sealing arrangements for filling holes. Examine compound for cracks

Examine for cracks and dirt deposits

Examine relay and alarm contacts, their operation, fuses etc. Check relay accuracy, etc.

Tan δ and Capacitance

  |